Request for Proposal - Advanced Metering Infrastructure

 

Advanced Metering Infrastructure Documents

Request for Proposals (PDF)

Request for Proposals (RTF)

Attachment A - Electric Meter Forms (XLS)

Attachment B - Meter Locations (XLS)

Attachment C - Pole Locations (XLS)

Advanced Metering Infrastructure Time Schedule

Time (EST) Deadline   Process Step
  12/8/2017 RFP advertised and issued to bidders
4:00 p.m. 12/28/2017 Bidders send an intention to bid letter via email to HLPD
4:00 p.m. 1/26/2018 Final RFP questions to HLPD  
2:00 p.m. 2/13/2018 HLPD to issue answers to all RFI's
2:00 p.m. 2/27/2018 HLPD to hold public RFP opening
  2/28/2018 HLPD to analyze RFP's  
  3/28/2018 HLPD to select proposal  
  3/29/2018 HLPD and Bidder to negotiate contract; start procurement process
  5/23/2018 First phase of equipment to arrive, installation to begin upon arrival
  11/12/2018 AMI Network backbone, software, 20% meters installed
  12/17/2018 Testing, commissioning, acceptance testing to be complete
  12/31/2018 Full scope of this RFP to be satisfied
*Note: All RFP milestone dates are subject to change at HLPD’s sole discretion.*

 


This website has been created and is maintained by the Hudson Light and Power Department. Any discrepancy between information provided on this website and the actual practices, policies, rate schedules charges, etc. is unintended. In all such cases, the actual practices, policies, rate schedules, charges, etc. of the Hudson Light and Power Department shall prevail.